Price list items added for the January 2022 price lists

1. CPSBWRAP<Bubble Wrap 12″ wide – Add-on cost for fragile items
(+)Included: 3/16″ economy grade bubble wrap in 12″ wide rolls with perforation every 12″ for easy tear off.Excluded: Labor to wrap, pack, or move fragile materials.
2. CPSBWRAP>Bubble Wrap 48″ wide – Add-on cost for fragile items
(+)Included: 3/16″ economy grade bubble wrap in 48″ wide rolls with perforation every 12″ for easy tear off.Excluded: Labor to wrap, pack, or move fragile materials.
3. EQCSFTRATrack – asphalt
(+)Included: Asphalt mix, road base, primer/tack coat, and labor and equipment to place and compact road base and asphalt paving.Excluded: Subgrade excavation, site preparation, and curbing.Quality: 2 1/2″ – 3″ compacted asphalt and 6″ compacted road base.
4. EQCSFTRCTrack – cinder/clay
(+)Included: Cinder top mix, compacted base fill, equipment, and installation labor.Excluded: Subgrade excavation, site preparation, and curbing.Quality: Compacted base 3″ and 3″ cinder top mix.
5. EQCSFTRPTrack – synthetic – polyurethane
(+)Included: Polyurethane coating system, striping, and installation labor.Quality: Poured in place approximately 13 mm thick.Included: Labor cost to remove the top coating of a synthetic running track and to discard in a job-site waste receptacle.(-)
6. EQCSFTRSTrack – synthetic – latex
(+)Included: Latex coating system, striping, and installation labor.Quality: Rake and spray approximately 10 mm thick.Included: Labor cost to remove the top coating of a synthetic running track and to discard in a job-site waste receptacle.(-)
7. FNCH2H4Header casing – 4″ – hardwood – 2 piece
(+)Included: 1″ x 4″ trim board, 1″ x 2″ trim board, finish nails, and installation labor.Quality: 4″ hardwood, oak, alder, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
8. FNCH2H6Header casing – 6″ – hardwood – 2 piece
(+)Included: 1″ x 6″ trim board, 1″ x 2″ trim board, finish nails, and installation labor.Quality: 6″ hardwood, oak, alder, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
9. FNCH2H8Header casing – 8″ – hardwood – 2 piece
(+)Included: 1″ x 8″ trim board, 1″ x 2″ trim board, finish nails, and installation labor.Quality: 8″ hardwood, oak, alder, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
10. FNCH2P4Header casing – 4″ – paint grade – 2 piece
(+)Included: 1″ x 4″ trim board, 1″ x 2″ trim board, finish nails, and installation labor.Quality: 4″ paint grade softwood, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
11. FNCH2P6Header casing – 6″ – paint grade – 2 piece
(+)Included: 1″ x 6″ trim board, 1″ x 2″ trim board, finish nails, and installation labor.Quality: 6″ paint grade softwood, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
12. FNCH2P8Header casing – 8″ – paint grade – 2 piece
(+)Included: 1″ x 8″ trim board, 1″ x 2″ trim board, finish nails, and installation labor.Quality: 8″ paint grade softwood, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
13. FNCH3H6Header casing – 6″ – hardwood – 3 piece
(+)Included: 1″ x 6″ trim board, 1″ x 2″ trim board, cove molding, finish nails, and installation labor.Quality: 6″ hardwood, oak, alder, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
14. FNCH3H8Header casing – 8″ – hardwood – 3 piece
(+)Included: 1″ x 8″ trim board, 1″ x 2″ trim board, cove molding, finish nails, and installation labor.Quality: 8″ hardwood, oak, alder, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
15. FNCH3P6Header casing – 6″ – paint grade – 3 piece
(+)Included: 1″ x 6″ trim board, 1″ x 2″ trim board, cove molding, finish nails, and installation labor.Quality: 6″ paint grade softwood, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
16. FNCH3P8Header casing – 8″ – paint grade – 3 piece
(+)Included: 1″ x 8″ trim board, 1″ x 2″ trim board, cove molding, finish nails, and installation labor.Quality: 8″ paint grade softwood, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
17. FNCH4H6Header casing – 6″ – hardwood – 4 piece
(+)Included: 1″ x 6″ trim board, 1″ x 2″ trim board, cove molding, finish nails, and installation labor.Quality: 6″ hardwood, oak, alder, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
18. FNCH4H8Header casing – 8″ – hardwood – 4 piece
(+)Included: 1″ x 8″ trim board, 1″ x 2″ trim board, cove molding, finish nails, and installation labor.Quality: 8″ hardwood, oak, alder, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
19. FNCH4P6Header casing – 6″ – paint grade – 4 piece
(+)Included: 1″ x 6″ trim board, 1″ x 2″ trim board, cove molding, finish nails, and installation labor.Quality: 6″ paint grade softwood, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
20. FNCH4P8Header casing – 8″ – paint grade – 4 piece
(+)Included: 1″ x 8″ trim board, 1″ x 2″ trim board, cove molding, finish nails, and installation labor.Quality: 8″ paint grade softwood, or equal.Included: Labor cost to remove header casing and to discard in a job-site waste receptacle.(-)
21. FNCHMRSHeader casing – multi-member – Detach <amp; reset
(+)Included: On site storage, finish nails, and installation labor.Notes: Labor cost to detach multi-member header casing, move to an adjacent room for storage, and reinstall at a later time.
22. WTRPOWD>Power distribution box – 100+ amp (per day)
(+)Included: Equipment cost for a portable power distribution box and short power cord (may be integrated). Based on 24 hours of use on the job-site.Excluded: Set-up, take down, and monitoring. Use WTREQ for set-up, take down, and/or monitoring, if needed.Quality: Elevated power distribution center may include various 120/240 outlets and/or other connection types and configurations (100 amp and greater).
Meets OSHA standards for temporary power connections on a job-site.
23. WTRPOWDW>Power distribution box – 100+ amp (per week)
(+)Included: Equipment cost for a portable power distribution box and short power cord (may be integrated). Based on 24 hours of use on the job-site.Excluded: Set-up, take down, and monitoring. Use WTREQ for set-up, take down, and/or monitoring, if needed.Quality: Elevated power distribution center may include various 120/240 outlets and/or other connection types and configurations (100 amp and greater).
Meets OSHA standards for temporary power connections on a job-site.

Price list items modified for the January 2022 price lists

1. CLNFINAL*Added text to Note field of (+) definition to clarify differences in final cleaning and activity-specific general clean-up.
2. CPSBWRAPModified description to reference width and modified material component yield in (+) assembly.
3. FRMDBP4Modified labor component in (-) assembly.
4. FRMDBP6Modified labor component in (-) assembly.
5. FRMDBPAD*Modified labor component in (-) assembly.
6. FRMJ10LFModified Included field of (+) definition to reference “solid blocking.”
7. FRMJ12LFModified Included field of (+) definition to reference “solid blocking” and “hanger brackets.”
8. FRMJ4LFModified Included field of (+) definition to reference “solid blocking.”
9. FRMJ6LFModified Included field of (+) definition to reference “solid blocking.”
10. FRMJ8LFModified Included field of (+) definition to reference “solid blocking.”
11. FRMRF12SFModified yield of material component FRMHBR210 in (+) assembly.
12. RFGFELTL*Modified Note field of (+) definition to reference “low-sloped” typically refers to roofs with a slope of 4/12 or less.

Material components added for the January 2022 price lists

1. CPSBWRAP<Bubble wrap – 3/16″ economy grade – 12″ wide
2. CPSBWRAP>Bubble wrap – 3/16″ economy grade – 48″ wide

Personal property items modified for the January 2022 price lists

1. ELCTVL35Changed description to TV – LCD / LED-LCD 30-39 in. – Standard grade
2. ELCTVL35Changed description to TV – LCD / LED-LCD 30-39 in.
3. ELCTVL35+Changed description to TV – LCD / LED-LCD 30-39 in. – High grade
4. ELCTVL45-Changed description to TV – LCD / LED-LCD 40-49 in. – Standard grade
5. ELCTVL45Changed description to TV – LCD / LED-LCD 40-49 in.
6. ELCTVL45+Changed description to TV – LCD / LED-LCD 40-49 in. – High grade
7. ELCTVL55-Changed description to TV – LCD / LED-LCD 50-59 in. – Standard grade
8. ELCTVL55Changed description to TV – LCD / LED-LCD 50-59 in.
9. ELCTVL55+Changed description to TV – LCD / LED-LCD 50-59 in. – High grade

Material components modified for the January 2022 price lists

1. CPSBWRAPModified description and unit type to represent LF.
2. LITHG*Replaced “globe” with “pendant” in the description.

Personal property item removed for the January 2022 price lists

1. ELCDVDRDDVD recorder – Single disk
2. ELCAVCF-Firewire cable 3 ft
3. ELCAVCFFirewire cable 6 ft
4. ELCAVCF+Firewire cable 12 ft
5. ELCAVCF++Firewire cable 25 ft
6. ELCTVL40-TV – LCD / LED-LCD 35-39 in. – Standard grade
7. ELCTVL40TV – LCD / LED-LCD 35-39 in.
8. ELCTVL40+TV – LCD / LED-LCD 35-39 in. – High grade
9. ELCTVL50-TV – LCD / LED-LCD 45-49 in. – Standard grade
10. ELCTVL50TV – LCD / LED-LCD 45-49 in.
11. ELCTVL50+TV – LCD / LED-LCD 45-49 in. – High grade
12. ELCTVL54-TV – LCD / LED-LCD 50-54 in. – Standard grade
13. ELCTVL54TV – LCD / LED-LCD 50-54 in.
14. ELCTVL54+TV – LCD / LED-LCD 50-54 in. – High grade

Miscellaneous changes made for the January 2022 price lists

  • Modified text of applicable labor Supporting Events to clarify assumptions for clean-up would be independent of any warranted final cleaning at the end of the job.

Future changes and additions to look for in upcoming price list publications

  1. Item(s) for full louvered double door.

Signifies changes to multiple items with similar selectors.